Oct 29

October construction update

Posted on October 29, 2020 at 1:59 PM by Diane Carmony

Sun City Water Main Replacement, Phase 1 in Palm Desert.

Contractor has completed installation of the water mains within Sub-Phase A and mainline installation has been completed in Subphase B. Some 128 out of 146 water services have been installed.

Traffic impacts: Some. Work to be coordinated with homeowners.
Water service disruptions: Some. Work to be coordinated with homeowners.

Ave. 66 Grade Separation Transmission Main in Mecca

Construction on the bridge has started and the waterline is scheduled to be installed beginning in early 2021.

Traffic impacts: Some. Work to be coordinated by the County of Riverside’s contractor. Water service disruptions: None.

Westside School Consolidation, Thermal Mutual Water Consolidation/Oasis Garden Mobile Home Park in Thermal

A livestream virtual groundbreaking ceremony was held on Oct. 6 for Westside School. Construction is underway.

Traffic impacts: Some. Work to be coordinated with the school.
Water service disruptions: Some. Work to be coordinated with the school.

Talavera Water Main Replacement in Indio

The contractor met with the HOA this month to review the completed punch list items and the project has been completed.

.